TM 5-5420-203-14
2-10. LOADING AND UNLOADING OPERATIONS.
Both the Class 60 and Class 70 bridges have been equipped with proper side lifting points for the lift of
the folded bridge by the attachment of a standard four-legged sling.
In addition, the individual quarter-sections of the Class 70 bridge can be lifted by attachment of a
two-legged sling. The quarter-sections can be lifted either by the two outboard lift points or diagonally
by attaching the sling to the outboard ramp-end lift point and the single inboard lift point (located where
the second tiedown from the center hinge used to be).
The Class 60 bridge' individual panels will continue to be lifted by the deck lift points. The Class
s
70 bridge will NOT be lifted at the deck points (the lift bars, will be removed).
The lift points and sling attachments for the folded bridge (Class 60 and Class 70) and the
individual sections (Class 70) are shown below.
Change 2 2-79