TM 5-5420-227-24
UNIVERSAL JOINT REPLACEMENT (Sheet 3 of 3)
4.
Position key (E) between front yoke (B) and shaft (F) and slide yoke (B) forward on shaft
(F) until it bottoms out.
5.
Using screw key, install setscrew (G).
Aline splines of yoke (D) and shaft (H), and slide yoke (D) on shaft (H).
6.
7.
Position tube assembly (J) between yokes (B and D) and rotate yoke (B) until both universal
joints (A) are alined, then slide yoke (D) forward.
Aline holes and manually start four screws (K) on each end of tube assembly (J).
8.
Using torque wrench and 7/16 inch crowfoot wrench, tighten eight screws (K) to 265
9.
to 325 lb-in (30 to 36 Nm).
NOTE
Replace any screws (K) which have been over torqued
beyond 325 lb-in (36 N m).
10.
11.
TA170286
End of Task
3-58