TM-5-5420-279-10
62
Fully lower the tilt rollers.
63
Add and boom further parallel modules as required.
64
Deploy the end beam guide adapters.
65
Add the end beam guides.
66
Add the 2 removable rollers at the white marks furthest from the crane.
67
Position the home bank end beam on the guides.
68
Add the home bank ramp and pin.
69
Reposition the slings on ramp to allow for the end beam.
70
Add the ramp module to the bridge.
71
Remove and stow the end beam guides, adapters, removable rollers and the tilt
rollers.
72
Remove flatracks V2 and T2 from the build site.
73
Place flatrack LVT on the build site.
74
Boom the bridge until the end plate of ramp contacts the bridge stops emergency.
75
Remove the home bank carriage shootbolts and lower the carriage lifting beam.
76
Attach the slings to the bridge lift points on the ramp.
77
Raise the bridge and release the bridge stops emergency once the bridge starts to
move.
78
Re-shootbolt the home bank carriage.
79
Release the tension in the cable.
80
Reverse the bridge to release the home bank carriage latches.
81
Release the carriage latches and boom the bridge forward.
82
Stop the bridge boom when the carriage restraint arms are fully extended.
83
Raise Bridge and release the far bank carriage shootbolts.
84
Lower the far bank end of the bridge to ground.
85
Un-sling the far bank carriage, raise and shootbolt.
86
Raise the bridge and release the home bank carriage shootbolts.
87
Lower the home bank end of the bridge to ground.
88
Un-sling the home bank carriage and raise.
6-5