TM 5-5420-280-10
0016 00
LAUNCH OF BRIDGE (Contd)
NOTE
If using LPU, perform step 63. If using CBT back-up
power, perform step 64.
63. Stop LPU. Refer to WP 0015 00.
64. Move PTO ENGAGE switch (10) to OFF position. PTO ENGAGE indicator (9)
will go out.
9
10
65. Check main power switch (11) to ensure it is in OFF position. (Switch is off
when key is in horizontal position.)
11
OFF POSITION
0016 00-29