TM 55-1945-205-10-2 0049 00 2 0049 00 2. Using a crowbar, raise the side female guillotine connectors (5) to release one outboard string (1). 3. Separate the outboard string (1) from the center string (2). 4. Repeat steps to separate outboard string (4) from the center string (2). 5. Stow the male and female connector guillotines. (WP 0052 00) 6. Using crane and slings, lift string out of the water for disassembly. END OF WORK PACKAGE 5 5