ARMY TM 5-5420-212-10-1
MARINE CORPS TM 08676A-10/1-1
DSC
Pallet Loads EOB1 and EOB2.
(12) Place four top panels on top of deck units.
(a)
Ensure that shoot bolts are put in locked position after panels are butted together.
(b)
Center top panels are over deck units.
EOB 1
EOB 2
(13) Place two junction panels on deck units between the top panels. Use timber packing (3 in x 8 in x 36 in)
between junction panels and deck units. Position the packing so that there is clearance between the junction
panel dowels and the deck units.
(a)
The long side of junction panels face down on the deck units.
(b)
The bottom of the junction panels face each other.
3-90