TM 55-1945-205-10-2
0015 00 1
0015 00
OPERATOR MAINTENANCE
ROLL-ON/ROLL-OFF DISCHARGE FACILITY
PLATFORM
OPERATION UNDER USUAL CONDITIONS
INITIAL SETUP:
Tools
Tool Kit, General Mechanics (Rail and Marine) (Item 7, WP 0121 00)
Life Preserver, Vest (Item 33, WP 0119 00)
Gloves, Mens and Womens (Leather Palm) (Item 25, WP 0119 00)
Goggles, Sun, Wind and Dust (safety) (Item 27, WP 0119 00)
Helmet, Safety (Item 29, WP 0119 00)
Crowbar (Item 16, WP 0119 00)
Hammer, Hand (10 lb Sledge) (Item 29, WP 0119 00)
Personnel Required
Seaman 88K
Equipment Condition
Module ISOPAK Disassembled. (WP 0008 00)
Operation Of Male And Female Guillotine Connectors. (WP 0009 00)
D-Ring/Cloverleaf Fittings And Deck Cleat Fittings Installed. (WP 0010 00)
Module String Assembled. (WP 0011 00)
Intermediate Section Assembled. (WP 0012 00)
RRDF Segment Assembled. (WP 0014 00)
PREPARATION FOR USE - ASSEMBLY OF PLATFORM
ASSEMBLE A FULL SIDE CONFIGURATION
:,1*
All personnel must wear personal flotation device, hard hat, safety shoes and gloves
during RRDF operations and maintenance. Failure to observe these precautions
could result in serious injury or death.
Do not handle ropes/lines by placing hands in bight of the line where it feeds into
cleats, etc. Place the hands on top or on the outside so that in an emergency the lines
can be released quickly to preclude being pulled into the equipment. Failure to follow
these precautions could result in serious injury or death.
1.
Maneuver sections together using warping tugs, ropes/lines, flush turn tubes and lift lugs so that the tapered
surfaces of male and female shear connectors mate together in general alignment.