TM 55-1945-205-10-2
0022 00 1
0022 00
OPERATOR MAINTENANCE
ROLL-ON/ROLL-OFF DISCHARGE FACILITY
EMERGENCY ANCHORING SYSTEM (EASY)
OPERATION UNDER USUAL CONDITIONS
INITIAL SETUP:
Tools
Tool Kit, General Mechanics (Rail and Marine) (Item 7, WP 0121 00)
Life Preserver, Vest (Item 33, WP 0119 00)
Gloves, Mens and Womens (Leather Palm) (Item 25, WP 0119 00)
Goggles, Sun, Wind and Dust (safety) (Item 27, WP 0119 00)
Helmet, Safety (Item 29, WP 0119 00)
Personnel Required
Seaman 88K
Equipment Condition
RRDF Assembled. (WP 0008 00)
PREPARATION FOR USE - INSTALLATION OF EASY ON PLATFORM
:,1*
All personnel must wear personal flotation device, hard hat, safety shoes and gloves
during RRDF operations and maintenance. Failure to observe these precautions
could result in serious injury or death.
1.
Position container at the upstream end of the RRDF platform.
2.
Ensure that the anchor end of the EASY container is located 24 in. from the upstream deck edge to allow enough
room for personnel to open the anchor-end container doors and allow the anchor to deploy properly.