TM 55-1945-205-10-4
0046 00 1
0046 00
OPERATOR MAINTENANCE
FLOATING CAUSEWAY
OFFSHORE ANCHOR MOORING LEGS
OPERATION UNDER USUAL CONDITIONS
INITIAL SETUP:
Tools
Tool Kit, General Mechanics (Rail and Marine) (Item 7, WP 0106 00)
Life Preserver, Vest (Item 31, WP 0104 00)
Gloves, Mens and Womens (Leather Palm) (Item 23, WP 0104 00)
Goggles, Sun, Wind and Dust (safety) (Item 25, WP 0104 00)
Helmet, Safety (Item 27, WP 0104 00)
Crowbar (Item 14, WP 0104 00)
Hammer, Hand (10 lb Sledge) (Item 26, WP 0104 00)
Gloves, Chemical (Item 22, WP 0104 00)
Goggles, Industrial (chipping, chemical) (Item 24, WP 0104 00)
Apron, Utility (Item 1, WP 0104 00)
Forklift Adaptor (Item 19, WP 0104 00)
Hook, Boat (Item 29, WP 0104 00)
Respirator, Air Filtering (Item 5, WP 0106 00)
Materials/Parts
Cleaner, Type II (Item 6, WP 0105 00)
Corrosion, Preventive Compound, Grade I (Item 7, WP 0105 00)
Corrosion, Preventive Compound, Grade II (Item 8, WP 0105 00)
Rag, Wiping (Item 16, WP 0105 00)
Personnel Required
Seaman 88K
PREPARATION FOR MOVEMENT - RECOVERY OF OFFSHORE ANCHOR MOORING LEGS
RECOVER OFFSHORE ANCHOR MOORING LEGS
:,1*
All personnel must wear personal flotation device, hard hat, safety shoes and gloves
during FC operations and maintenance. Failure to observe these precautions could
result in serious injury or death.
127(
Packing of the mooring legs in the offshore container is normally done ashore.
The following procedure is typical for the recovery and stowage of the offshore anchor
mooring legs.
1.
Using a boat hook, capture shackle (retrieval pendant) (1) on 30 ft buoy cable (2).