TM 55-1945-205-24-4
0177 00 1
0177 00
UNIT LEVEL MAINTENANCE
FLOATING CAUSEWAY
LIGHT TOWER ENGINE UPPER RADIATOR HOSE
REPLACEMENT
INITIAL SETUP:
Tools
Tool Kit, General Mechanics (Rail and Marine) (Item 54, WP 0253 00)
Gloves, Mens and Womens (Leather Palm) (Item 16, WP 0253 00)
Goggles, Sun, Wind and Dust (Safety) (Item 18, WP 0253 00)
Helmet, Safety (Brown) (Item 20, WP 0253 00)
Life Preserver, Vest (Item 25, WP 0253 00)
Gloves, Chemical (Item 14, WP 0253 00)
Goggles, Industrial (Chipping, Chemical) (Item 17, WP 0253 00)
Apron (Item 1, WP 0253 00)
Respirator, Air Filtering (Item 40, WP 0253 00)
Pan, Drain (Item 33, WP 0253 00)
Materials/Parts
Antifreeze (Item 2, WP 0252 00)
Spill Clean-Up Kit, Hazardous Material (Item 39, WP 0252 00)
Personnel Required
Engineer 88L
Equipment Condition
Light Tower Battery Negative Lead Terminal Removed. (WP 0131 00)
REMOVE LIGHT TOWER ENGINE UPPER RADIATOR HOSE
WARNING
All personnel must wear personal flotation device, hard hat, safety shoes and gloves during
FC operations and maintenance. Failure to observe these precautions could result in
serious injury or death.
1.
Position drain pan under drain cock (1).