TM 5-5420-203-14
2-3. ASSEMBLY AND PREPARATION FOR USE OF MLC 60 - CONT
Preparation for Assembly of Bridge Separated at Center Hinges. Refer to page 2-34.
(2)
c. Assembly of the Bridge Separated into Eight Sections.
Bridge separated into eight sections
EQUIPMENT CONDITIONS:
General Mechanic's Tool Box, SC 5180-90-N26
TOOLS/EQUIPMENT:
Sledge Hammers (8-10 lb) (two required)
Pry Bars (5-6 ft) (three required)
Wrench, Adjustable, (item 3, Appendix B) (two required)
Lifting Device, 15,000 lb Minimum Lift Capacity
Sling, Multiple Leg
Cribbing, 4 x 4 x 6 ft
SUPPLIES:
Ten
PERSONNEL:
NOTE
When possible, assemble the bridge on a hard surface, within a unit compound, on an old
road bed, etc.
Installation of Holder Bracket (Near-Shore and Far-Shore).
(1)
Install holder bracket (1) on
(a)
diaphragm (2). Align with holes on
either side of top of diaphragm.
Place flat washer (3) on bolt (4) and
install through bracket (1). Install
lock washer (5) and nut (6) on bolt
(4). Tighten nut/boltassembly.
Repeat for remaining bolt (4).
Repeat step (a) for remaining holder
(b)
bracket (1) on diaphragm (2).
2-14 Change 2