NOTE
To ensure proper installation of the clevis, lift a test load after the winch cable is assembled. The wire
will not be visible through the inspection hole after the test load is lifted.
(16) Adjust cable tensioner (5) as follows:
(a) Pay out cable and tighten nut (11) until cable (2) in passing through cable tensioner (5) without slippage.
(b) Tighten nut (11) one half turn more and tighten nut (10).
(c) Verify proper operation of cable tensioner in both directions.
(17) Secure cable assembly (2) to boom (1) and pay in cable.
(18) Raise boom (1), remove blocking and lower and secure boom (1).
Figure 4-35. Winch Cable Assembly (Winch Model PG-115-043R), Replace.
FOLLOW-ON MAINTENANCE: Install bay (para. 2-27).