2-17. General. This section contains procedures to place the ribbon bridge into short term storage.
2-18. Short Term Storage.
a. Perform operator’s level before operation PMCS procedures in accordance with TM 5-5420-209-12.
b. Perform unit level weekly and monthly PMCS procedures in accordance with TM 5-5420-209-12.
c. Perform operator’s and unit level lubrications procedure in accordance with LO 5-5420-209-12.