3-21.
PALLETIZATION - LINK REINFORCEMENT
Link reinforcement components are carried on two pallets, LRS-1 and LRS-2. To load the pallets, perform the
steps as described below.
a.
Pallet Load LRS-1
(1)
Place twenty long links on pallet in four layers of five links each.
(a)
The side flanges of the links must interlock with the previous layer. Flanges must not sit on top of each
other.
(b)
End of links shall be flush with front end of pallet.
LRS 1
(2)
Place four short links across long links, and four cable puller handles between the long links and short links.
Short links shall be side by side and centered over long links.
LRS 1
(3)
Place two footwalks on top of long links. Both footwalks are placed on load upside down and at each end of
links.