TM 5-5420-278-10
0026 00
0026
HIGH-BANK LAUNCH OF BAY (Contd)
at. Secure bay. (Refer to WP 0029 00, Securing Interior Bay After Launch or
refer to WP 0028 00, Securing Ramp Bay After Launch.)
au. After BEB crew disconnects IRB lifting sling from bay, move HIGH IDLE
switch (1) to ON position and hold WINCH switch (2) in IN position until top
of snatch block (8) is 9 in. (23 cm) from bottom of winch extension
assembly (5), then release switch (2).
av. Hold MAIN FRAME switch (4) in LOAD position until bottom of snatch block
hook (9) is approximately 9 ft (2.8 m) above edge of bank, then release switch
(4).
aw. Move HIGH IDLE switch (1) to OFF position.
ax. Move CBT forward until approximately 30 ft (9 m) from edge of bank, then
apply service brake (13), move transmission selector lever (12) to N (neutral),
and pull PARKING BRAKE control (11) out.
13
12
11
2
4
3