TM-5-5420-279-10
Section V. OPERATING CRANE IN EMERGENCY CONDITIONS
CRANE EMERGENCY PROCEDURES
12.12.1.1
If the maximum load capacity is exceeded, all working movements that increase the
load moment and `lower boom' are switched off.
12.12.1.2
Shortly before the maximum load is reached, the crane overload warning lamp
12.12.1.3
The crane load is reduced by working movements, which decrease the load moment
Figure 12. 30, once this is
done the full working functions are restored.