TM 5-5420-280-10
0019 00
BRIDGE OPERATION (Contd)
3. Bridge Preparation Prior to Retrieval.
a.
If recovering bridge by helicopter, refer to WP 0021 00.
b.
Remove four marker poles from bridge. Refer to WP 0008 00.
c.
If installed, remove anchorage from bridge. Refer to WP 0018 00.
d.
If bridge is covered with dirt and debris, clean external surfaces of bridge.
END OF WORK PACKAGE
0019 00-5/6 blank