TM 5-5420-280-10
0023 00
TRANSLOADING PALLET TO PALLETIZED LOAD SYSTEM
TRAILER (PLST) (Contd)
11. Ensure NATO power cable (8) is disconnected from NATO slave receptacles (9)
and (11), and main power switch (10) is in OFF position.
8
9
10
11
CAUTION
Prior to backing CBT, trailer drawbar must be all the
way in, or damage to equipment may result.
Ensure trailer drawbar is down against ground during
transfer operations, or damage to equipment may result.
Both trailer bumper points must be under truck bump
plate, and at least one trailer bumper point must
contact bump plate. Trailer bumper point not contacting
transporter bumper stop cannot exceed
0.5 in. (12.7 mm), or BP will miss main rail guides and
damage to equipment may result.
NOTE
Ensure transload roller bar rollers ride over top of
trailer bumper points and are centered over or on
trailer guides when backing up CBT.
12. Back up transporter so trailer bumper points (13) are under flange and contact
bump plate (12), apply service brake (16), move transmission selector
lever (15) to N (neutral), and pull parking brake control (14) out.
14
15
16
13
15
0023 00-5