TM 55-1945-205-10-4
0037 00 1
0037 00
OPERATOR MAINTENANCE
FLOATING CAUSEWAY
LIGHT TOWERS
OPERATION UNDER USUAL CONDITIONS
INITIAL SETUP:
Tools
Tool Kit, General Mechanics (Rail and Marine) (Item 7, WP 0106 00)
Life Preserver, Vest (Item 31, WP 0104 00)
Gloves, Mens and Womens (Leather Palm) (Item 23, WP 0104 00)
Goggles, Sun, Wind and Dust (safety) (Item 25, WP 0104 00)
Helmet, Safety (Item 27, WP 0104 00)
Personnel Required
Seaman 88K
PREPARATION FOR MOVEMENT - REMOVAL OF LIGHT TOWERS
REMOVE LIGHT TOWER
WARNING
All personnel must wear personal flotation device, hard hat, safety shoes and gloves
during FC operations and maintenance. Failure to observe these precautions could
result in serious injury or death.
NOTE
The following procedures is typical for the forward and aft light tower units to be stowed in
the ISO container, except the light tower must be removed from the aft light tower unit.
1.
Prior to lowering tower, perform the following:
a.
Position LAMP 1 through LAMP 4 switches (1), (2), (3) and (4) off.
HOURMETER
OFF
RUN
START
PRE
HEAT
FUEL LEVEL
MAIN
BREAKER
RECEPTACLE
120 V 20A
RECEPTACLE
240 V 20A
PUSH TO
RESET
LAMP
2
LAMP
1
LAMP
4
LAMP
3
4
2
6
7
3
1
5