TM 55-1945-205-10-4
0043 00 1
0043 00
OPERATOR MAINTENANCE
FLOATING CAUSEWAY
MOORING BITTS
OPERATION UNDER USUAL CONDITIONS
INITIAL SETUP:
Tools
Tool Kit, General Mechanics (Rail and Marine) (Item 7, WP 0106 00)
Life Preserver, Vest (Item 31, WP 0104 00)
Gloves, Mens and Womens (Leather Palm) (Item 23, WP 0104 00)
Goggles, Sun, Wind and Dust (safety) (Item 25, WP 0104 00)
Helmet, Safety (Item 27, WP 0104 00)
Crowbar (Item 14, WP 0104 00)
Hammer, Hand (10 lb Sledge) (Item 26, WP 0104 00)
Chain, ½ in. General Purpose (Item 12, WP 0104 00)
Forklift Adapter (Item 19, WP 0104 00)
Push Rod (Item 42, WP 0104 00)
Personnel Required
Seaman 88K
PREPARATION FOR MOVEMENT - REMOVAL OF MOORING BITTS
REMOVE MOORING BITT
:,1*
All personnel must wear personal flotation device, hard hat, safety shoes and gloves
during FC operations and maintenance. Failure to observe these precautions could
result in serious injury or death.
Attempting to remove mooring bitts from the FC in higher sea conditions than Sea
State 0 could cause injury or possible death to personnel and/or damage equipment.
1.
Use fork lift and lift chain to support mooring bitt (1).