(7)
(8)
(9)
(10)
(11)
(12)
(13)
NOTE
Start disassembly from downstream end of bridge.
Have boat secure to bay being removed.
Ensure four bay/bay connectors (7) are unlatched.
Unlatch two (only one on ramp bay) roadway/roadway connectors (8).
Lower handrails (8).
Open hydraulic pump access covers (10), close manual vent valves (11), set pump control levers (12) to
TRANSPORT position, and close covers (10).
Install T wrench (13) on lower lockpin screw (14), turn counterclockwise, and retract lower lockpin.
Repeat Step (12) for remaining lower lockpin screw and move bay to retrieval site.
Figure 2-29. Bridge Recovery Swinging Bridge Method (Sheet 2 of 3).
(14) Engage (toward roadway) four (only two on ramp bay) roadway/bow ponton foldlock
latches (16).
(15) Unlatch four roadway-to-bow ponton bridge latches (17).
2-100
TM 5-5420-209-12