Figure 2-16. High Bank Launch of Bay (Sheet 6 of 12).
Place transmission in neutral and engage PTO.
Install cable hook (20) in boom anchor (21).
Raise boom (14) fully and pay out cable.
Install snatch block (22) on cable (6).
Connect lifting sling (23) to snatch block (22).
NOTE
If a ramp bay is being launched, connect the longer two lines of the lifting sling to the ramp end bow lift
points. When launching an interior bay, all four lines should be of equal length.
(25) Connect four lifting sling lines (24) to bay lifting and anchoring pins (25).