n. Loads required
From Table 3-12, determine the truck and trailer toads required for the bridge.
TABLE 3-12. MGB Pallets SS
Pallet Type
Erection
Bridge
Total
4 - 5
1
1
2
No. of Bays
6 - 7
8 - 9
1 0 - 1 2
1
1
1
2
3
4
3
4
5
N O T E
Additional vehicles are required to transport personnel. Erection pallets may
be partial depending on the bridge being built.
o. Manpower and construction time
From Table 3-13, determine the manpower and construction time requirements
TABLE 3-13. Working parties and building times on good sites
(a)
Single Story Single Span
4-5 Bays
6-8 Bays
9-1 2 Bays
(b)
(c)
(d)
Working party
1 + 8
1 + 1 6
1
+16
Time by day (hours)
1/2
3/4
1
Time by night (hours)
3/4
1
1 1/4
NOTES:
1. All timings exclusive of work on approaches.
2. Add 20 percent for unskilled personnel.
3. Add 30 percent for inclement weather.
4. Add 30 percent for adverse site conditions.
p. Final design
During the preceding design process, the information necessary to fill in the blanks below would have been
obtained. Fill in these figures in the pro-forma, at this point the design is considered complete.
a. No. of Bays
b. LNCG Setting
c. Set-up of RB
and Packing Required
d. Bearing : NB
FB
e. TruckTrailer Loads
f. Manpower Required
g. Time to Construct