TM 5-5420-278-10
0023 00
0023 00-4
UNLOADING BAY TO GROUND (Contd)
j. Ensure winch cable hook (1) is securely connected to bays lifting lug (3) with
the hook end facing up and toward bay (4). Ensure latch (2) is closed.
NOTE
In case of emergency while RCU is in use, push red
POWER EMERGENCY STOP switch to shut down
operation of LHS.
Operator will perform steps k through ab using RCU.
k. Hold WINCH switch (5) in IN position until slack in winch cable is removed,
then release switch (5).
NOTE
Perform step l if unloading ramp bay or step m if
unloading interior bay.
l. Check to ensure both foldlocks (6) and travel latch (7) are in their closed
positions at connecting end of ramp bay.
m. Check to ensure both foldlocks (8) and travel latch (9) at both ends of interior
bay are in their closed positions.
6
6
8
7
1
4
2
3
5
RAMP BAY