TM-5-5420-279-10
Slide Frame Decking Panel Stowage
3.5.6.1
Refer to Figure 3. 24 and stow the walkway decking panels as described below:
(i)
Lift the walkways fitted at the rear of the launching frame (Nos. 4, 5 and 6) and
stow under the launching frame. Ensure that they are stowed to the rear of the
launching frame (the end by the articulator cylinders), as, if stowed in the wrong
place they will be crushed as the A-frame is rotated down.
(ii)
Unpin and remove the safety rails from the two location holes in the folding
walkways.
(iii)
Place the walkway safety rails in their stowage locations on the previously stowed
walkways below the rear of the launching frame.
(iv)
Remove the removable slide frame decking panels (Nos. 1, 2, 3, and the two
double panels) from their deployed positions and stow in the chassis well at the
rear of the crane.