TM-5-5420-279-10
3.9.6.4
Connect tag lines to the handles at each end of the bridge module above the jaws to
assist in controlling the module when lifting operations begin. If building from the right
attach both tag lines to the right-hand side handles, if building from the left attach tag lines
to left-hand side.
3.9.6.5
Operate the lift controls on the crane and lift the parallel module.
Figure 3. 33 Bridge Module Opening
686A659
Figure 3. 34 Bridge Module Closing
3.9.7.1
Configure the module lifting beam to the center position for module closing.
3.9.7.2
Operate the controls on the crane to position the bridge module lifting beam in position to
attach it to the bridge module.
3.9.7.3
Connect the bridge module lifting beam to the closing sling located between the decking
panels of the bridge module, ensure that the lifting beam runs across the module.
3.9.7.4
Operate the lift controls on the crane and slowly lift the bridge module.
3.9.7.5
The parallel module will slowly close as the module is lifted.