TM-5-5420-279-10
Bridge Module Lifter in POSITION 2 of Ramp Module
4.9.4.13
Disconnect the single leg sling from the crane hook.
4.9.4.14
Retrieve the two end beam slings and secure them around the end beam at the
bridge lift points, to ensure a straight lift and attach a guide rope (refer to Chapter 3
4.9.4.15
Place two removable rollers onto the second section of the slide frame at the white
marks on slide frame section three.
4.9.4.16
Remove the retaining R clip and deploy the end beam guide adapters, located at the
end of section one of the slide frame nearest the crane.
4.9.4.17
Locate the two end beam guides onto the adapters ensuring that they are securely
seated and that the locking arms are in the up position.
4.9.4.18
Operate the crane controls on the crane and position the crane hook above the end
beam slings.
CAUTION
To prevent damage to the lifting slings it is important that care is exercised when
connecting the slings to the crane hook. Ensure that the sling is fitted correctly and does
not become trapped by the hook safety clip.
4.9.4.19
Attach the end beam slings to the crane hook, ensuring that they are secure.
4-74