TM-5-5420-279-10
Table 8.5 Operators PMCS (After) - (continued)
Location
Not Fully Mission
Item
Item to
Procedure
Interval
Capable If:
No.
Check
Service
1
170
After
Launch frame
Open inspection doors (1) to gain
winch control
access to the winch control
manifold
manifold.
a) Check as far as possible for
Class III leak evident.
hydraulic fluid leaks.
(b) Check electrical cables as far as
Damaged or chafed
possible for damage and chafing.
cables evident.
171
After
Launch frame
Open inspection doors (1) to gain
articulator
access to the articulator manifold
manifold and
and synchronization manifold.
synchronization
(a) Check as far as possible for
Class III leak evident.
manifold
hydraulic fluid leaks.
(b) Check electrical cables as far as
Damaged or chafed
possible for damage and chafing.
cables evident.
(c) Close R/H manifold cover doors.
8-55