TM-5-5420-279-10
Check for any deformation of the end beam guide body. Report any
damage/deformation to maintenance.
End beam guide adapter.
Check the end beam guide adapter assembly for deformation of side plates
and hinge. Report any deformation to maintenance.
Tilt rollers (See Operation 44).
Check all shootbolts for ease of use. Report any defect to maintenance.
Check the tilt roller pivot for seizure/deformation. Report any
seizure/deformation to maintenance.
Check the tilt roller head pivot point for seizure. Report seizure to
maintenance.
72. Remove flatracks V2 and T2 from build site.
73. Place flatrack LVT on build site.
74. Boom the bridge forwards until end plate of ramp contacts the bridge
stops emergency.
Booming forward - difficult/noisy.
Check that the bridge is not continuously rubbing against A-frame side wear
pad. Check and level A-frame.
Check for free rotation of tilt and A-frame rollers during booming. Report
seized rollers to maintenance.
Check the V notch in A-frame side rubbing pad for wear limit. Report wear to
maintenance.
75. Remove home bank carriage shootbolts and lower carriage lifting beam.
Check the home bank carriage lift beam to main carriage body shootbolts for
deformation/seizure. Report deformation/seizure to maintenance.
Check that the chest pack is in BRIDGE LIFT Mode.
Carriage sling shootbolt will not retract.
Check that the R clip is removed.
Check for seizure/deformation of the pin. Report seizure or deformation to
maintenance.
Carriage lifting beam will not lower.
Check for dirt build up or binding of the mating faces on the upper and lower
halves of the forward carriage. Clean as required.
Check that the winch cable is seated in the grooves of the grooved pulleys.
If winch cable is not seated in grooves inform maintenance.
Check that the winch is operating correctly. Report any defect to
maintenance
76. Attach slings to bridge lift points on ramp.
Sling will not route through lifting point.
Check that the slings are being connected to ramp bridge lift points, and
NOT end beam lift points.
Clear the lifting pocket of any dirt. Clean as required.
Check for integrity of lifting pin and bracket. Report any defect to
maintenance.
9-45