TM 55-1945-205-24-4
0117 00 2
0117 00
2.
Loosen two screws (2).
3.
Pull wires (1) straight out of circuit breaker (3).
4.
Firmly grasp circuit breaker (3) at the midline of the load bank (4) rotate circuit breaker (3) outward from
mounting cleats (5) and discard.
INSTALL PERSONNEL SHELTER ELECTRICAL DISTRIBUTION PANEL TWO POLE
CIRCUIT BREAKER
1.
Install the back side of the new circuit breaker (3) into mounting cleats (5).
2.
Rotate circuit breaker (3) onto the midline of the load bank (4) until it snaps into position.
WARNING
3.
Coat wires (1) with dielectric grease.
4.
Remove tags and install wires (1) into circuit breaker (3) and tighten two screws (2).
5.
Install personnel shelter load distribution panel access cover. (WP 0115 00)
END OF WORK PACKAGE