3.
Remove spanner nuts (5) from strain relief (3).
4.
Remove strain relief (3) from junction box (6).
5.
Remove two screws (7) securing junction box (6) to bulkhead and discard junction box (6).
INSTALL PERSONNEL SHELTER OUTLET BOX
1.
Position new junction box (6) on bulkhead.
2.
Install two screws (7) in junction box (6) and secure to bulkhead. Tighten screws (7).
3.
Install strain relief (3) in junction box (6).
4.
Install spanner nuts (5) on strain relief (3) and tighten.
5.
Push wiring harness (4) through strain relief (3).
6.
Install two screws (1) and clamp (2) on strain relief (3). Tighten screws (1).
7.
Install personnel shelter ground fault circuit interrupter receptacle. (WP 0122 00)
8.
Install personnel shelter hospital grade straight blade electrical receptacle. (WP 0121 00)
END OF WORK PACKAGE