TM 5-5420-203-14
RAMP SECTION MISCELLANEOUS COMPONENTS REPLACEMENT (Sheet 2 of 2)
INSTALLATION
INSTALL RAMP SECTION MISCELLANEOUS COMPONENTS.
a. Place two screws (3) with two flat washers (6) thru pipe anchor clamp (4). Position clamp on
section (12) at angle bracket (5). Install two new lock washers (2) and two nuts (1) on two screws
(3). Tighten two nuts (l).
b. Place flat washer (11) on screw (9). Install screw (9) through spring tension clip (10).
Install screw, flat washer, and spring tension clip in mounting hole located on ramp section
(12). Place new lock washer (8) and nut (7) on screw (9). Tighten nut (7).
c. Place two machine screws (16) in pipe flange (17) and install on ramp section (12). Place
two flat washers (15), new two lock washers (14) and two nuts (13) on two machine screws
(16). Tighten nuts (13).
d. Install two screws (20) through ramp section (12). Place lifting bar (21) on two screws
from underside of ramp section (12).
e. Place two new lock washers (19) and two nuts 18) on two screws (20). Tighten nuts.
f. Thread threaded screw insert (22) into ramp section (12).
END OF TASK
3-59