ARMY TM 5-5420-212-10-1MARINE CORPS TM 08676A-10/1-1p.Manpower and construction timeFrom Table 3-36, determine the manpower and construction time requirements.Table 3-36. Working Parties and Building Time on Good Sites - DS 13-22 Bay with LRSDouble Story Single Span 13-22 Bays w/LRSa13 Bays(b)14 - 18 Bays(c)19 - 22 Bays(d)Working Party2 + 322 + 322 + 32Time by Day (hours)22 3/43Time by Night (hours)344 1/2NOTES:1.All timings exclusive of work on approaches.2.Add 20 percent for unskilled personnel.3.Add 30 percent for inclement weather.4.Add 30 percent for adverse site conditions.q.Final DesignDuring the preceding design process, the information necessary to fill in the blanks below would have beenobtained. Fill in these figures in the pro-forma, at this point the design is considered complete.a.2E +Baysb.LNCG Settingc.CRB Settingd.RRB Settinge.Bearing: NBFBf.Truck/Trailer Loadsg.Manpower Requirementsh.Time to Constructr.Design Pro-FormasThis paragraph contains the design pro-formas, which are to be photocopied and used to record the final designinformation.3-48
Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business