ARMY TM 5-5420-212-10-1MARINE CORPS TM 08676A-10/1-1TABLE 1-5. Work Parties for MGBBridge LengthsWork Party4 and 5 bay (26ft - 7.9m, 32ft - 9.8m) SSB1 NCO + 8 personnel6 thru 12 bay (38ft - 11.6m thru 50ft - 15.2m) SSB1 NCO + 16 personnelAll DSB’s1 NCO + 24 personnelAnchorage Party for DSB’s (if required)8 personnelLink Reinforcement Party1 NCO + 8 personnelb.Approximate building times for various bridges are given in Table 16. Time is calculated from arrival on site tothe opening of bridge.TABLE 1-6. Building Times (good conditions)Single StoryDouble Story(without reinforcement)Double Story(with reinforcement)4-5Bay6-8Bay9-12Bay1-4Bay5-8Bay9-13Bay14-18Bay19-22Bay13Bay14-18Bay19-22BayTime byDay (hrs)½¾1¾11½1¾222¾3Time byNight (hrs)¾11¼1¼1½22¾3344½NOTE:All timings exclusive of work on approaches.Add 20 percent for unskilled personnel.Add 30 percent for inclement weather.Add 30 percent for adverse site conditions.1-14
Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business