MANUALLY LOADING BAP FROM GROUND
WARNING
Winch frame must be locked to BAP prior to loading
BAP from ground. Failure to comply may result in
damage to equipment or injury to personnel.
NOTE
When both levers are in UP position, the winch frame is
locked to the BAP. Perform steps b and c if levers are in
DOWN position.
The following manual mode operations using cab
control box are to be performed only when normal
AUTO mode electric circuit is malfunctioning.
During all transporter operations, CBT operator will
drive and be responsible for operation of LHS via the
cab control box or remote control unit. The assistant
will act as a ground guide, be responsible for directing
operator using hand signals, and assist operator as
needed.
a. If bay is loaded on BAP, inspect load and make sure it is secure.
b. Remove quick-release pin (2) from stud (3) at both sides of winch frame (1).
c. Swing lever (4) up so that end of stud (5) is through hole in lever (4), and
install quick-release pin (2) on stud (5) at both sides of winch frame (1).
5
1
2
3