TM 5-5420-280-10
0026 00
OPERATION OF CBT BACK-UP POWER FOR BRIDGE LAUNCH OR RETRIEVAL
(Contd)
5. Remove dust cap (4) from NATO slave receptacle (3), located on pallet adjacent
to auxiliary reservoir (2), and connect power cable (1) to NATO slave
receptacle (3).
2
1
3
4
6. Check main power switch (5) to ensure it is in ON position. (Switch is on when
key is in vertical position.)
5
ON POSITION
0026 00-4