TM 55-1945-205-10-4
0022 00 1
0022 00
OPERATOR MAINTENANCE
FLOATING CAUSEWAY
PERSONNEL SHELTER
OPERATION UNDER USUAL CONDITIONS
INITIAL SETUP:
Tools
Tool Kit, General Mechanics (Rail and Marine) (Item 7, WP 0106 00)
Life Preserver, Vest (Item 31, WP 0104 00)
Gloves, Mens and Womens (Leather Palm) (Item 23, WP 0104 00)
Goggles, Sun, Wind and Dust (safety) (Item 25, WP 0104 00)
Helmet, Safety (Item 27, WP 0104 00)
Materials/Parts
Antiseize Compound (Item 2, WP 0105 00)
Personnel Required
Seaman 88K
Equipment Condition
Generator Container Installed On Trident Pierhead. (WP 0021 00)
PREPARATION FOR USE - INSTALLATION OF PERSONNEL SHELTER
INSTALL PERSONNEL SHELTER ON TRIDENT PIERHEAD
:,1*
All personnel must wear personal flotation device, hard hat, safety shoes and gloves
during FC operations and maintenance. Failure to observe these precautions could
result in serious injury or death.
127(
Personnel shelter must be on the same platform section with generator container.
1.
Using crane, lift personnel shelter onto trident pierhead.
2.
Position personnel shelter in desired location.
3.
Tie personnel shelter at four corners to trident pierhead using tie down straps.