TM 55-1945-205-10-4
0023 00 1
0023 00
OPERATOR MAINTENANCE
FLOATING CAUSEWAY
LIGHT TOWERS
OPERATION UNDER USUAL CONDITIONS
INITIAL SETUP:
Tools
Tool Kit, General Mechanics (Rail and Marine) (Item 7, WP 0106 00)
Life Preserver, Vest (Item 31, WP 0104 00)
Gloves, Mens and (Leather Palm) (Item 23, WP 0104 00)
Goggles, Sun, Wind and Dust (safety) (Item 25, WP 0104 00)
Helmet, Safety (Item 27, WP 0104 00)
Personnel Required
Seaman 88K
PREPARATION FOR USE - INSTALLATION OF LIGHT TOWER UNIT
REMOVE FORWARD AND AFT LIGHT TOWER UNIT FROM CONTAINER
:,1*
All personnel must wear personal flotation device, hard hat, safety shoes and gloves
during FC operations and maintenance. Failure to observe these precautions could
result in serious injury or death.
127(
The following procedure is typical for the forward and aft light tower units installed in the
ISO container, except the light tower must be installed on the aft light tower unit.
1.
Release tiedowns and remove light tower trailer drawbar (1) and drawbar jack (2) from ISO container.
:,1*
2.
Using forklift pull light tower trailer and pallet from container.
3.
Install trailer drawbar (1) and drawbar jack (2) on light tower trailer with bolt (3) and nut (4) and set up on
drawbar jack (2).