TM 55-1945-205-10-4
0034 00 1
0034 00
OPERATOR MAINTENANCE
FLOATING CAUSEWAY
ONSHORE ANCHOR MOORING LEGS
OPERATION UNDER USUAL CONDITIONS
INITIAL SETUP:
Tools
Tool Kit, General Mechanics (Rail and Marine) (Item 7, WP 0106 00)
Life Preserver, Vest (Item 31, WP 0104 00)
Gloves, Mens and Womens (Leather Palm) (Item 23, WP 0104 00)
Goggles, Sun, Wind and Dust (safety) (Item 25, WP 0104 00)
Helmet, Safety (Item 27, WP 0104 00)
Crowbar (Item 14, WP 0104 00)
Hammer, Hand (10 lb Sledge) (Item 26, WP 0104 00)
Forklift Adaptor (Item 19, WP 0104 00)
Personnel Required
Seaman 88K
Equipment Condition
Floating Causeway Assembled. (WP 0015 00)
OPERATING PROCEDURES - DEPLOY ONSHORE ANCHOR MOORING LEGS
UNPACK ONSHORE CONTAINER
:,1*
All personnel must wear personal flotation device, hard hat, safety shoes and gloves
during FC operations and maintenance. Failure to observe these precautions could
result in serious injury or death.
127(
The following procedure is typical for the assembly and deployment of the onshore
anchor mooring legs.
1.
Position onshore anchor container parallel with the structure on the deck of the first FC section from beach.
2.
Unlatch and open container side doors.
:,1*
Ensure that each door is latched in the open position before releasing control of the
door or lock each door in the closed position when the doors are not being handled.
Failure to comply could result in death or serious injury to personnel.
3.
Secure doors open with locking hooks