TM 55-1945-205-24-2
0121 00 2
0121 00
2.
Tag and pull wire (2) straight out of circuit breaker (3)
3.
Firmly grasp circuit breaker (3) at the midline of the load bank (4), rotate circuit breaker (3) outward and discard.
INSTALL PERSONNEL SHELTER ELECTRICAL DISTRIBUTION PANEL SINGLE POLE
CIRCUIT BREAKER
1.
Install the back side of the new circuit breaker (3) into mounting cleat (5).
2.
Rotate circuit breaker (3) onto the midline of the load bank (4) until it snaps into position.
WARNING
3.
Coat wire (2) with silicone grease.
4.
Install wire (2) into circuit breaker (3) and remove tag and tighten two screws (1).
5.
Install personnel shelter load distribution panel access cover. (WP 0118 00)
END OF WORK PACKAGE