TM 55-1945-205-24-4
0156 00 2
0156 00
2.
Remove
ballast
box (3) from light tower frame (2) and discard.
INSTALL LIGHT TOWER BALLAST BOX
1.
Position new ballast box (3) on light tower frame (2).
2.
Install four bolts (1) through
ballast
box (3) and tighten.
3.
Install light tower ballasts. (WP 0159 00)
4.
Install light tower ballast box cover. (WP 0158 00)
5.
Install light tower ballast box panel end. (WP 0157 00)
6.
Install light tower control panel key switch. (WP 0151 00)
7.
Install light tower control panel 125 volt breaker. (WP 0150 00)
8.
Install light tower control panel toggle switches. (WP 0149 00)
9.
Install light tower control panel main
circuit breaker
. (WP 0148 00)
10. Install light tower control panel twist lock outlet. (WP 0147 00)
11. Install light tower control panel duplex outlet. (WP 0146 00)
12. Install light tower control panel fuel gage. (WP 0145 00)
13. Install light tower control panel hour meter. (WP 0144 00)
14. Install light tower control panel. (WP 0160 00)
15. Install light tower battery negative lead terminal. (WP 0131 00)