ARMY TM 5-5420-212-10-1
MARINE CORPS TM 08676A-10/1-1
(4)
Connect nose roller to bankseat beam (para. 4-10).
(5)
Position extended jack in landing roller pedestal, and place closed landing roller pedestal and landing
roller in front of roller beam and clear of building line.
NOTE
The landing roller pedestal Is used when constructing 9 through 12 bay single story bridges.
(6)
Add bay 2
(7)
Lift girders and move pedestals to panel point 2p4.
(8)
Unlock rollers. Lift girders and boom bridge forward until panel point 1p2 is over roller beam rollers; lock
rollers.
(9)
Connect top panels of bay 3 to top panels of bay 2, using a headless panel pin. This pin is required for
connection of launching nose cross girder post.
(10) Lift girders and move pedestals to panel point 3p7. Building pedestals are now in their final position and
require no further movement.
5-21