(9)
Add bay 4.
(10) Add first heavy launching nose and landing roller pedestal assembly.
(11) Add 2N1 and 3N1, booming nose and securing with panel pin as each is added.
WARNING
DO NOT try to construct any more nose without counterweight top panels and deck units,
otherwise injury to personnel and damage to equipment will occur.
(12) To add counterweight.
(a)
Position four top panels and four deck units on rear of bridge, as shown above.
(b)
Ensure that counterweights are as far to rear of bridge as possible.
(c)
Stack counterweights as shown to provide space for addition of remaining nose sections.
(d)
Secure counterweights to bridge girders with two cargo tie-down straps.
5-33