ARMY TM 5-5420-212-10-1
MARINE CORPS TM 08676A-10/1-1
5-17.
PICKET TYPE INSTALLATION
Before ramps are added, Install pickets as follows:-
(1)
Use hammer to drive pickets into bank at 1 ft (0.3 m) intervals along the outside end of near bankseat
beam.
5-18.
APPROACH GUY INSTALLATION
During construction, anchorage pins will be used in place of panel pins, as described in the following steps. These
procedures are written for the use of two or four cables at each end of bridge. Step (7) can be performed immediately
after arrival on site, depending on the availability of personnel.
Installation
(1)
Insert far bank anchorage pins, instead of panel pins, in junction of first and second bay. Anchorage pin
must be inserted from inside of bridge.
NOTE
Bridge must be boomed until anchorage pin Is In front of roller beam before anchorage lug can be
attached.
5-47