ARMY TM 5-5420-212-10-1
MARINE CORPS TM 08676A-10/1-1
Section II. NORMAL SITES
6-1.
ASSEMBLY- DOUBLE STORY - 2E + 12 BAY
a.
Set up and align roller beams
(1)
Assemble front roller beam (FRB) and rear roller beam (RRB) and position on site (para. 4-5b.).
(2)
Ensure roller beams are level.
b.
Assembly
NOTE
Throughout bridge assembly the NCOIC must monitor the height and level of roller beams. The
height must be set to achieve an acceptable working height. Roller beams must be level so that
components connect/disconnect properly.
(1)
Assemble end of bridge (EOB) and first bay (para. 4-8).
(2)
Position extended jack vertically in Mk1 landing roller pedestal and place closed landing roller pedestal
and landing roller next to front roller beam.
(3)
Fit nose roller to bankseat beam (para. 4-10).
6-29