(27) Lower near bank end of bridge using jacks (para. 4-20), davits (para. 4-21) or crane (para. 4-22).
(28) If approach surface is to be improved, do so at this time.
(29) Hook seven long ramp units to near bankseat beam. Ensure anti lift-lugs are engaged (para. 4-24).
(30) Lay decking, starting on near bank end of bridge (para. 4-25).
(31) If exit surface is to be improved, do so at this time.
(32) Hook seven long ramp units to far bankseat beam. Ensure anti lift-lugs are engaged.
(33) Fit curbs, starting on near bank end of bridge (para. 4-26).
(34)Put bridge guide markers in place (para. 4-26).
(35) After bridge has passed inspection, put bridge classification signs in place.
(36) Make sure all erection equipment is away from roadway. The bridge is now ready for use.