ARMY TM 5-5420-212-10-1
MARINE CORPS TM 08676A-10/1-1
6-4.
ASSEMBLY 2E + 22 BAY - W/O LINK REINFORCEMENT
a.
Set up and align roller beams
(1)
Assemble capsill roller beam (CRB) front roller beam (FRB) and rear roller beam (RRB) and position on
site as shown (para. 4-5c.).
(2)
Ensure roller beams are level.
CAUTION
It is very Important that roller beams be correctly positioned at this time. If they are not, serious
problems will arise during construction due to the bridge deviating from the centerline.
b.
Assembly
(1)
Perform steps b. (1) thru (9) in paragraph 61 to assemble end of bridge, bays 1 thru 5 and launching
nose up to 6N1, with LRP secured on launching nose.
(2)
Add three double story nose sections (1N2, 2N2, 3N2), booming the nose forward and securing with a
panel pin in nose roller as each double story nose is added (para. 4-12c.). Ensure that launching nose
link is vertical.
(3)
Add bay 6 including sway brace.
6-45