ARMY TM 5-5420-212-10-1
MARINE CORPS TM 08676A-10/1-1
Section II. NORMAL SITES.
7-1.
ASSEMBLY 2E + 22 BAY-LINK REINFORCED
a.
Set Up and Align Roller Beams
(1)
Assemble capsill roller beam (CRB) front roller beam (FRB) and rear roller beam (RRB) and position on
site as shown (para. 4-5c.).
(2)
Lock FRB and RRB rollers; lock capsill roller beam rocking rollers (para. 4-5).
CAUTION
It is very Important that roller beams be correctly positioned at this time. If they are not, serious
problems will arise during construction due to the bridge deviating from the centerline.
b.
Assembly
NOTE
Throughout bridge assembly the NCOIC must monitor the height and level of the roller beams.
The height must be set to achieve an acceptable working height. Roller beams must be level so
that components connect/disconnect properly.
(1)
Position link components on site in preparation for assembly.
7-14