TM 5-5420-226-20-3
UNIVERSAL JOINT REPLACEMENT (Sheet 1 of 7)
PROCEDURE INDEX
PAGE
PROCEDURE
Removal
Inspection
Installation
Thickness gage
TOOLS: 13/16 in. socket with 1/2 in. drive
Oxy-acetylene welding equipment
2 in. extension with 1/2 in. drive
10 in. flat file
Socket wrench handle with 1/2 in. drive
Torque wrench with 3/8 in. drive
Torque wrench with 1/2 in. drive (0-175 lb-ft) (0-237 Nm)
(0-200lb-in.) (0-23 Nm)
Diagonal cutting pliers
Adapter 1/2 in-3/8 in.
Slip joint pliers
Alining punch
Pinch bar
Crowbar
Hammer
92 lb. minimum capacity hoist
3/4 in. socket with 1/2 in. drive
1-1/2 in. combination box and open end wrench
SPECIAL TOOLS: Center punch (Figure F-9, Appendix F)
Paint brush (Item 73, Appendix D)
SUPPLIES: Locking wire (Item 61, Appendix D)
Dry cleaning solvent (Item 55, Appendix D)
Brazing alloy (Item 74, Appendix D)
Welding flux (Item 75, Appendix D)
Rags (Item 65, Appendix D)
Industrial goggles (Item 71, Appendix D)
Rubber gloves (Item 72, Appendix D)
Two
PERSONNEL:
REFERENCES:
Remove transmission shroud (page 9-2)
Remove transmission shroud support (page 9-15)
Remove turbosupercharger outlet elbow (page 7-75)
Block both tracks front and rear, place transmission selector lever
in neutral (N) and make sure brake is released
Pull transmission mounting guide towards rear
Go on to Sheet 2