NOTE
There are four load receiving pins on each IRB-R and each IRB-I.
All load receiving pins on ramp and interior bays are removed and
installed the same way.
REMOVAL
1.
Remove two screws (2) and retainer strap (3) from load receiving pin (1) and recess block (4).
2.
Remove load receiving pin (1) from recess block (4).
3.
Perform steps 1 and 2 to remove remaining load receiving pins.
INSTALLATION
1.
Install load receiving pin (1) on recess block (4).
2.
Install retainer strap (3) on load receiving pin (1) and recess block (4) with two screws (2).
3.
Perform steps 1 and 2 to install remaining load receiving and rafting bracket pins.